Telangana State Medical Services & Infrastructure Development Corporation (TSMSIDC)

S.No HO Division Works Sanctioned Works Completed Works In Progress Works not Started
1 Nizamabad Division 15 0 0 15
TOTAL 15 0 0 15








S.No Project Id Project Name District Agreement Date Completion Date as per Agreement Tech Sanction Amount Value of work done Stage of Work
2 19 Construction of 50 bedded Critical Care Block at DH Kamareddy Kamareddy 09/03/2023 08/06/2024 23,75,00,000 Not Started
3 70 Construction of additional floor (3rd floor with sheds) and additional wards in old TB block in District Hospital building, Kamareddy Kamareddy 09/03/2023 08/07/2023 4,53,00,000 Not Started
4 71 Upgradation of attached Government General Hospital at Kamareddy in Kamareddy District. Kamareddy 20/10/2022 19/10/2023 10,00,00,000 Not Started
5 72 Providing additional facilities to 1st year medical college at Kamareddy in Kamareddy District Kamareddy 09/05/2023 08/05/2024 12,68,00,000 Not Started
8 110 Construction of 30 bedded hospital building at Pitlam in Kamareddy District. Kamareddy 17/04/2023 16/04/2024 10,70,00,000 Not Started
12 150 Construction Of SROs / ROs Building at Kamareddy in Kamareddy Dist. Kamareddy 10/02/2017 09/02/2018 63,00,000 Not Started
13 160 Construction of Mini Stadium at Domakonda (V&M) Kamareddy Kamareddy 08/12/2016 07/12/2017 2,65,00,000 Not Started
14 161 Construction of Mini Stadium at Jukkal (V&M) in Kamareddy District. Kamareddy 12/02/2020 11/11/2020 1,00,00,000 Not Started
15 164 Construction of Green field stadium at Bichkunda(V&M) in Kamareddy District) Kamareddy 07/04/2016 06/04/2017 2,10,00,000 Not Started
1 16 Construction of 50 bedded Critical Care Block at GMC, Nizamabad Nizamabad 21/11/2022 20/07/2023 23,75,00,000 Not Started
6 101 Upgradation of Community Health Centre, Yellareddy, Nizamabad District from 30 bedded hospital to 100 bedded Hospital. Nizamabad 27/02/2023 26/02/2024 15,00,00,000 Not Started
7 103 Establishment of new 100 Area Hospital at Bheemgal, Nizamabad District. Nizamabad 14/11/2022 13/11/2023 35,00,00,000 Not Started
9 119 Construction of 30 bedded hospital building at Varni in Nizamabad District. Nizamabad 07/07/2023 06/07/2024 10,70,00,000 Not Started
10 123 Establishment of (50) bedded CHC at Kotagiri, Nizamabad Dist. Nizamabad 08/06/2023 07/06/2024 13,00,00,000 Not Started
11 149 Construction Of SROs / ROs Building at Bheemgal in Nizamabad Dist. Nizamabad 24/09/2016 23/08/2017 63,00,000 Not Started